Durban port congestion crisis: 20-day vessel delays choke medicine supplies and car exports
Transnet clears six critical medicine vessels as Durban terminal races to ease congestion
Sunday World details Transnet and Durban Gateway Terminal's recovery programme — equipment refurbishment, new reachstackers and straddle carriers, alternative berthing — after clearing six medicine vessels.
By Sunday World reporter · Sunday World
Excerpt
The piece foregrounds the terminal's multi-phase recovery: 16 new reachstackers and empty-container handlers by end-November, 26 second-hand straddle carriers by Q1 2027, 12 new straddles and 16 rubber-tyred gantry cranes through 2027-2028, plus a stabilised Navis N4 operating system and a truck appointment system. Transnet is considering diverting pharmaceutical containers to alternative terminals, and DGT attributes the underlying problems to years of under-investment. The framing follows Transnet's own recovery narrative. (Publish date not shown on the page; estimated 21–22 November from content and syndication timing.)
Read the full article on Sunday World ↗